ITQAN Works
Document Control
โš™ Config ๐Ÿ“‚ LOCAL
T1 โ€” Submittals
T2 โ€” Correspondence
T3 โ€” RFIs
T4 โ€” Contracts
T5 โ€” Close-out
โšก Priority Actions
Dashboard
๐Ÿ‘ท Contractors
๐Ÿ—บ Journey Map
๐Ÿ“Š Views
๐Ÿ“– Glossary
๐Ÿงญ Classify
๐ŸŽ“ Scenarios
๐Ÿ“– Glossary โ€” Acronyms & Terms
Quick reference for all specialist terms used in this app
Jump:
๐Ÿ“„ Document Type Codes (26)
DWG
Shop Drawings
T1 submittal. Detailed construction drawings prepared by the Main Contractor showing exactly how designed elements will be fabricated and installed. Common prefixes: S-* Structural, A-* Architectural, M-* Mechanical, E-* Electrical, P-* Plumbing, TW-* Temporary Works, FF-* Fit-out.
MAT
Material Approvals
T1 submittal. Product data sheets and compliance samples submitted for approval before procurement. Includes mill certificates (steel), batch certificates (concrete admixture), technical brochures.
MTH
Method Statements
T1 submittal. Step-by-step description of how the Main Contractor will carry out a specific operation โ€” sequencing, equipment, personnel, safety. Requires HSE Manager co-signature.
ITP
Inspection and Test Plans
T1 submittal. Structured plan defining what will be inspected, when (hold / witness / test points), by whom, and to what acceptance criteria. Consultant QA must co-sign.
DES
Design Submittals & Calculations
T1 submittal. Contractor-Designed Portion (CDP) submissions, structural calculations, welding procedures (WPS), vendor prequalifications. High design liability โ€” never fast-track.
PLN
Pre-Construction Management Plans
T1 submittal. Six sub-types: PQP (Project Quality Plan), HSE Plan, EMP (Environmental Management Plan), TMP (Traffic Management Plan), WMP (Waste Management Plan), ERP (Emergency Response Plan). Gates mobilisation.
PER
Personnel Approvals
T1 submittal. CVs for key project roles: Project Manager, QA/QC Manager, HSE Manager, Commissioning Manager. Gates mobilisation.
PRG
Programme and Schedule
T1 submittal. Baseline programme, monthly updates, look-aheads, recovery programmes. Baseline approval gates the first Interim Payment Certificate.
PMT
Statutory Permits and Authorizations
T1 submittal. Building permits, crane permits, road-closure permits, environmental authorizations. The permit itself โ€” not correspondence about it.
SMP
Samples and Mock-ups
T1 submittal. Physical finish samples, colour swatches, room mock-ups. Retain physically, never return โ€” becomes the approved benchmark.
OAM
O&M Manuals and Product Data
T1 submittal (initial approval). Operation & Maintenance manuals for installed systems. Also compiled into T5 handover dossier at completion โ€” LIFECYCLE document.
BIM
Coordination Drawings (Building Information Model)
T1 submittal. Federated 3D model showing all disciplines together. Clash detection reports. Zero clashes on a fresh model is a red flag, not success.
CMP
Commissioning Plans and Procedures
T1 submittal. Test & Commissioning methodology, precommissioning plans. Bridges to T5 test records at handover โ€” LIFECYCLE document.
LTR
Correspondence Letter
T2 track. Formal letters, site instructions, notices under contract clauses. Time-barred notices sit here (Clause 20.1, EOT, Force Majeure).
MIN
Meeting Minutes
T2 track. Minutes of progress, technical, kick-off, and handover meetings. Unchallenged minutes are deemed accepted โ€” silence is agreement.
NCR
Non-Conformance Report
T2 track. Formal record of quality failure, specification deviation, test failure, or workmanship defect. Never close on verbal assurance โ€” requires documented RCA (Root Cause Analysis) and CAP (Corrective Action Plan).
PRO
Progress Reports
T2 track. Daily Site Reports (DSR), weekly progress summaries, monthly formal reports, site diaries. No DSR entry = fatal to future claim on that day.
HSE
HSE Incident and Safety Records
T2 track. Incident/accident reports, near-miss reports, Permit-to-Work (PTW) records, emergency drill records, safety observations.
RFI
Request for Information
T3 track. Formal question from the Main Contractor to the Consultant / Engineer about drawing conflicts, missing details, spec ambiguity, or coordination clashes. Time-bounded response required.
VO
Variation Order
T4 track. Formal instruction changing the scope of works โ€” add, omit, or substitute โ€” with associated cost and time impact. Requires priced quotation + technical justification before authorization.
CTR
Contract Documents
T4 track. Insurance certificates, performance bonds, parent-company guarantees, Advance Payment Guarantees (APG), sub-contract agreements.
CNT
Contract Amendments
T4 track. Head contract, supplementary agreements, deeds of variation, assignment / novation. Signed by the PARTIES, not the Engineer.
TER
Termination and Suspension
T4 track. Suspension notices (Clause 16.1), notices to remedy (Clause 15.1), termination notices (Clause 15.2 for cause, 15.5 for convenience). EXISTENTIAL โ€” engage legal counsel.
ABL
As-Built Drawings
T5 track. Drawings marked "AS-BUILT" or with "-AB" suffix showing what was actually constructed vs approved design. Cross-reference the T1 shop drawing โ€” LIFECYCLE.
SNR
Snag / Test / Commissioning Records
T5 track. Snag lists (pre-PC), punch lists, test results, commissioning records. Snag โ‰  defect (different clause, different remedy).
HND
Handover Documents
T5 track. Statutory completion certificates, Taking-Over Certificate (TOC), handover dossier, training records, spare parts, DLP defect notifications, Performance Certificate.
โš–๏ธ Contractual / FIDIC Terms (33)
FIDIC
Fรฉdรฉration Internationale Des Ingรฉnieurs-Conseils
International Federation of Consulting Engineers. Publishes the standard-form construction contracts used on most Gulf mega-projects. Not a party to the contract โ€” a publisher. Rainbow Suite: Red Book (build), Yellow Book (design-build), Silver Book (EPC โ€” Engineering, Procurement, Construction โ€” turnkey), Green Book (short-form), Pink Book (MDB).
SLA
Service Level Agreement
The response deadline agreed for a submittal review, RFI answer, or correspondence action. Typical: 14 days for standard, 21 days for complex, 7 days for RFI. Chase at 50%/80% checkpoints; 30%/60% for Critical Path.
EOT
Extension of Time
Contractor claim for additional time on the programme due to a delay event not of their fault. Time-barred under FIDIC Sub-Clause 20.1 (28-day notice + 42-day full claim). Missing notice = claim barred.
LDs
Liquidated Damages
Pre-agreed daily amount withheld from the Main Contractor for late completion. Cap typically 10% of contract value. Money withheld pending Practical Completion or Taking-Over.
PC
Practical Completion
The point at which the works are substantially complete and can be handed over to the Employer, even if minor snags remain. Triggers TOC issue, DLP start, retention first-moiety release, LDs stop.
TOC
Taking-Over Certificate
Formal certificate issued at Practical Completion transferring possession and care of the works from Contractor to Employer. Sectional TOC possible โ€” each section starts its own DLP clock.
DLP
Defects Liability Period
Period (typically 12 months) after Taking-Over during which the Main Contractor must remedy any defects at their own cost. Ends with issue of the Performance Certificate.
IPC
Interim Payment Certificate
Monthly certificate issued by the Engineer valuing work completed and materials delivered. Adjustments for VOs, retention, LDs. DC clock starts at date of receipt.
DAB
Dispute Adjudication Board
Independent panel constituted to resolve disputes during construction. Referral is typically the first formal step before arbitration. Strictest time-bar of all โ€” FREEZE THE FILE.
APG
Advance Payment Guarantee
Bank guarantee backing the advance payment (typically 10-20% of contract value) given to the Main Contractor at start. Reduces pro rata as advance is recovered from IPCs.
CAR
Contractor's All Risks Insurance
Primary construction insurance covering physical loss/damage during works. UAQ typically named as co-insured. Track expiry AND that UAQ is named โ€” verify both, never assume.
MDB
Multilateral Development Bank
World Bank, ADB (Asian Development Bank), IsDB (Islamic Development Bank) etc. FIDIC publishes a Pink Book with MDB-specific amendments for projects funded by these banks.
FM
Force Majeure
Exceptional event beyond the Main Contractor's control (war, natural disaster, epidemic) preventing performance. FIDIC Clause 19. TIME-BARRED notice required.
CDP
Contractor-Designed Portion
Element of the works where design responsibility sits with the Main Contractor (facades, curtain walls, specialist MEP). Design liability sits with Main Contractor โ€” never fast-track approval.
PQP
Project Quality Plan
Main Contractor's document defining how they will manage quality on the project โ€” procedures, ITPs, non-conformance handling, QA/QC organization. Part of PLN pre-construction plans.
EMP
Environmental Management Plan
Main Contractor's document defining environmental controls โ€” emissions, noise, dust, discharge, protected species. Part of PLN. Ongoing regulatory obligations attached.
TMP
Traffic Management Plan
Main Contractor's document defining vehicular access, traffic routing, road closures, and pedestrian safety around the site. Part of PLN.
WMP
Waste Management Plan
Main Contractor's document defining segregation, storage, and disposal of construction waste. Part of PLN. Environmental audit trail.
ERP
Emergency Response Plan
Main Contractor's document defining response to emergencies โ€” fire, medical, evacuation, environmental incident. Part of PLN. Drill records prove ERP is real, not shelf-document.
WPS
Welding Procedure Specification
Documented welding procedure for structural steel fabrication. Must be approved BEFORE fabrication starts. Typically submitted with matching PQR.
PQR
Procedure Qualification Record
Record of qualification tests proving that a specific welder using a specific WPS produces welds meeting specification. Submitted alongside WPS.
FAT
Factory Acceptance Test
Test of equipment at the manufacturer's factory BEFORE delivery to site โ€” chiller, switchgear, generator, fire pump. Separate from site ITPs.
SAT
Site Acceptance Test
Test of equipment after installation on site โ€” confirms delivery, installation, and functional integration in situ. Prerequisite for commissioning.
IR
Inspection Request
Main Contractor's request for the Consultant to witness a specific inspection point defined in an approved ITP. Typically 24-48 hours notice.
WIR
Work Inspection Request
Alternative name for IR used on some Gulf projects. Same purpose: Main Contractor requesting Consultant's witness inspection.
MoM
Minutes of Meeting
Written record of what was discussed, decided, and actioned in a meeting. Same as MIN docType. Unchallenged MoM = deemed accepted.
PTW
Permit to Work
Formal authorization for high-risk work โ€” hot work (welding), confined space, working at height, electrical isolation. Must be CLOSED at end of shift.
LOTO
Lock Out Tag Out
Safety procedure isolating and tagging energy sources (electrical, mechanical) so equipment cannot be re-energized during maintenance. Typically a PTW prerequisite.
BBS
Behavioural-Based Safety
Safety programme focused on observing and correcting worker behaviour rather than just conditions. Safety observations are the leading indicator of BBS culture.
QMS
Quality Management System
Documented system defining how the Main Contractor manages quality end-to-end โ€” typically ISO 9001-based. PQP is a project-specific instance.
BOQ
Bill of Quantities
Priced schedule of measured work items forming part of the contract. Rates in the BOQ are used for VO pricing and IPC valuation.
MDR
Master Document Register
The comprehensive register of every project document โ€” status, revision, dates, links. This app is UAQ's MDR for the MASAR project.
SI
Site Instruction
Formal written instruction from the Engineer to the Main Contractor directing a specific action on site. Classic variation trigger โ€” flag Commercial.
๐Ÿ‘ค Project Roles (16)
DC
Document Controller
The role you occupy. Responsible for receipt, verification, registration, routing, tracking, and transmittal of all project documents. NOT the technical reviewer.
PM
Project Manager
Senior manager responsible for delivering the project. Both UAQ and Main Contractor have their own PMs. Escalation point for critical issues.
QA
Quality Assurance
Preventive processes ensuring quality is built in โ€” procedures, training, audits, PQP. Broader than QC.
QC
Quality Control
Reactive processes checking finished work meets specification โ€” inspections, testing, NCR resolution. Narrower than QA.
HSE Manager
Health, Safety, and Environment Manager
Senior HSE role responsible for HSE Plan, PTW system, incident investigation, drills, statutory notifications. Co-signs Method Statements (MTH).
MEP Coordinator
Mechanical, Electrical, and Plumbing Coordinator
UAQ role coordinating MEP disciplines and reviewing MEP drawings (M-* / E-* / P-*) and coordination BIM. Owns clash resolution decisions.
RE
Resident Engineer
Consultant's senior on-site engineer with delegated Engineer authority โ€” issues instructions, chairs technical meetings, signs off inspections. Often the certifying authority in T5.
IC
Independent Checker
Chartered engineer external to the Main Contractor providing independent verification of Temporary Works designs. Must sign the Independent Design Check certificate.
CM
Commercial Manager
Senior commercial role managing contract, payments, variations, claims, disputes. Both UAQ and Main Contractor have their own. Owner of VO pricing decisions on their side.
DM
Design Manager
Main Contractor's senior role managing all design activity โ€” coordinating consultants, shop drawing production, technical clarifications. Countersigns DWG submissions internally.
TD
Technical Director
Main Contractor's most senior technical role with company-level authority. Countersigns high-risk submissions. Escalation point when Design Manager cannot resolve.
PT Sub-Contractor
Post-Tensioning Sub-Contractor
Specialist sub-contractor performing post-tensioned concrete design and installation. Their approval stamp must be present on S-* drawings involving PT (Post-Tensioned) elements.
Sub-Contractor
Sub-Contractor (Sub-Con)
Company contracted BY the Main Contractor to perform part of the works. Prequalification is T1 Card 7. Sub-Contract agreement is T4 Card 2.
Engineer
Engineer (FIDIC role)
The party appointed by the Employer to administer the contract. In FIDIC Red Book, the Engineer issues determinations (Clause 3.7), certifies IPCs, values VOs. May be UAQ internal or a separate consulting firm.
Employer
Employer (FIDIC role) / Client
The party commissioning the works. In this project, UAQ is the Employer. Pays the Main Contractor. Takes over the works at PC. Owner of the completed asset.
Consultant
Consultant
Firm providing design or engineering services to the Employer (or the Main Contractor for CDP). Answers RFIs. May be appointed as Engineer under FIDIC.
๐Ÿ›๏ธ Regulatory / Statutory (10)
SDAIA
Saudi Data and Artificial Intelligence Authority
Kingdom of Saudi Arabia regulator responsible for enforcing the Personal Data Protection Law (PDPL). Data residency and consent obligations attach to processing personal data of KSA residents.
PDPL
Personal Data Protection Law (KSA)
KSA data protection law, fully enforceable since September 2024 under SDAIA. Requires data residency, breach notification, subject rights. This app must operate within PDPL boundaries.
MISA
Ministry of Investment of Saudi Arabia
KSA ministry regulating foreign investment. Foreign national must obtain MISA investor registration before establishing a commercial entity in KSA.
SAIP
Saudi Authority for Intellectual Property
KSA agency responsible for trademarks, patents, copyrights. Class 42 trademark filing recommended before public launch of a software product bearing a brand.
MOL
Ministry of Labour
Regulator of employment matters โ€” work visas, contracts, labour disputes, Saudization. Incident reports involving injuries must be notified to MOL within statutory timeframes.
Civil Defence
Civil Defence (CD)
Authority responsible for fire safety, life safety, and civil defence approvals. Their approval is a T5 completion prerequisite โ€” without CD certificate, no occupancy.
Municipality
Municipality (local authority)
Local government authority issuing building permits, occupancy certificates, and construction-related regulatory approvals. Municipality completion certificate is a T5 handover prerequisite.
MOMRAH
Ministry of Municipal & Rural Affairs & Housing
KSA ministry overseeing municipalities and housing. Regulates building codes, zoning, and municipal permit systems.
CNTXT
CNTXT (Aramco-affiliated cloud reseller)
Exclusive reseller of Google Cloud Platform (GCP) services in KSA. Any commercial GCP procurement for KSA-residency workloads requires CNTXT.
KSA
Kingdom of Saudi Arabia
Jurisdiction of the UAQ MASAR project. Legal framework governing the works includes Saudi Building Code (SBC), PDPL (data protection under SDAIA), MOMRAH regulations for municipal approvals, and Saudi Council of Engineers registration for signatories.
๐Ÿš๏ธ Project-Specific (7)
UAQ
Umm Al Qura for Construction and Development
The Employer/Client for the MASAR Destination project. All UAQ reference numbers on documents originate from UAQ's master system.
MASAR
MASAR Destination
The mega-project this app supports. Multi-billion-SAR (Saudi Riyal) development in Kingdom of Saudi Arabia. UAQ is the Employer.
ITQAN
ITQAN (ุฅุชู‚ุงู† โ€” mastery)
The internal reference code prefix used by this Document Control system. Stays behind the scenes โ€” never shown to the Main Contractor. Also the brand name for the ITQAN Works software portfolio.
GSC
Gulf Star Contracting
One of the main contractors on the MASAR project. Sample name used in illustrative scenarios in this app.
MACE
MACE
One of the main contractors on the MASAR project.
TECH
TECH
One of the main contractors on the MASAR project.
FOA
FOA
One of the main contractors on the MASAR project.
๐Ÿ“ File / Procedure Conventions (17)
Rev A
Revision A (first submission)
First formal submission of a document. If rejected, next submission is Rev B (never a new Rev A).
Rev B / C / D
Revision B, C, D (resubmissions after rejection)
Subsequent revisions after rejection. Rev B = 2nd, Rev C = 3rd, Rev D = 4th. Rev D and beyond signal serious quality issue โ€” escalate to PM. Each resubmission must include Response-to-Comments matrix.
S-*
Structural drawing prefix
Drawing number starts with S- (e.g. S-101, S-215). Route to UAQ's Structural Engineer.
A-*
Architectural drawing prefix
Drawing number starts with A- (e.g. A-101, A-500). Route to UAQ's Architectural Lead.
M-*
Mechanical drawing prefix
Drawing number starts with M- (e.g. M-410, M-415). Route to UAQ's MEP Coordinator.
E-*
Electrical drawing prefix
Drawing number starts with E- (e.g. E-210, E-500). Route to UAQ's MEP Coordinator.
P-*
Plumbing drawing prefix
Drawing number starts with P- (e.g. P-320, P-410). Route to UAQ's MEP Coordinator.
TW-*
Temporary Works drawing prefix
Drawing number starts with TW- (e.g. TW-101). Scaffolding, formwork, falsework, propping, hoisting arrangements. Requires Independent Design Check certificate.
FF-*
Fit-out drawing prefix
Drawing number starts with FF- (e.g. FF-101). Interior fit-out, partitions, ceilings, finishes. Route to UAQ's Interior Designer primary, Architectural Lead secondary.
FC
For Construction
Drawing purpose stamp indicating the drawing is approved for construction use. The site may build to this revision.
FA
For Approval
Drawing purpose stamp indicating the drawing is submitted for approval. Once approved, becomes FC (For Construction). Starts a full SLA clock.
FI
For Information
Drawing purpose stamp indicating the drawing is issued for information only, not for approval. Does NOT start an SLA clock. Recipient acknowledgment only.
AB
As-Built
Drawing purpose stamp indicating the drawing shows what was actually constructed vs the approved design. Compiled into T5 handover dossier.
Presence Check
Presence Check (Receipt Verification)
DC's check at Receive step confirming the transmittal covering letter, all listed attachments, and all pages are present. Failure = return unregistered (T1 only; T2/T3/T4/T5 register first).
50% / 80% Chaser
SLA Chaser Checkpoints
DC sends written chasers to the reviewer at 50% and 80% of the SLA period. For Critical Path items, thresholds shift to 30% and 60% โ€” earlier escalation for downstream-blocking documents.
CP
Critical Path
The longest sequence of dependent activities determining the project completion date. A delay to any Critical Path activity delays the whole project. CP-flagged documents get earlier chaser thresholds (30%/60% vs 50%/80%).
MEP
Mechanical, Electrical, Plumbing
Umbrella term for building services disciplines. On drawings and BIM models, MEP appears as compound prefix (e.g. M-410 for Mechanical drawing 410, E-500 for Electrical, P-320 for Plumbing). MEP Coordinator role owns clash detection between these disciplines.
Submittal Register
๐Ÿ“– Submittal Guide โ–ผ
0
Rejected
0
Expected
0
Total
Status
All
Pending
Overdue
Approved
Rejected
Legacy
Expected
Document Type
All Types
๐Ÿ“ Shop Drawings ยท DWG
๐Ÿงฑ Material Approvals ยท MAT
๐Ÿ“‹ Method Statements ยท MTH
โœ… ITPs ยท ITP
๐ŸŽจ Samples & Mock-ups ยท SMP
๐Ÿ“š O&M ยท OAM
๐ŸŽฏ Design ยท DES
๐Ÿ“‹ Pre-Con Plans ยท PLN
๐ŸงŠ BIM ยท BIM
๐Ÿ”ง Commissioning ยท CMP
๐Ÿ‘ค Personnel ยท PER
๐Ÿ“… Programme ยท PRG
๐ŸŽซ Permits ยท PMT
Discipline
All Disciplines
Civil
Arch
Mech
LEGEND: ๐Ÿ“ DWG โ€” Shop Drawing ๐Ÿงฑ MAT โ€” Material Approval ๐Ÿ“‹ MTH โ€” Method Statement โœ… ITP โ€” Inspection & Test Plan ๐ŸŽจ SMP โ€” Sample / Mock-up ๐Ÿ“š OAM โ€” O&M / Product Data ๐ŸŽฏ DES โ€” Design Submittal ๐Ÿ“‹ PLN โ€” Pre-Construction Plan ๐ŸงŠ BIM โ€” BIM & Coordination ๐Ÿ”ง CMP โ€” Commissioning Plan ๐Ÿ‘ค PER โ€” Personnel Approval ๐Ÿ“… PRG โ€” Programme ๐ŸŽซ PMT โ€” Statutory Permit
โšก Proactive signals Tap any card for the full list ยท Tap Ask Claude for AI guidance
First pass approval
โ€”
% approved without rejection
Avg review days
โ€”
Receipt to response
Open submittals by discipline
Reviewer workload
Chasers unconfirmed โ€” poka-yoke tracker
Revision history โ€” multiple cycles
Critical โ€” overdue and due within 3 days
n8n AUTOMATION
โš  Not yet connected. The rows below are the planned automations, not live ones โ€” no reminders are currently being sent automatically. Use the SLA Tracker on each document's Review/Consult step for now.
SLA 50% reminder โ†’ reviewerPLANNED
SLA 80% chaser โ†’ reviewer + managerPLANNED
Overdue escalation โ†’ PMPLANNED
Weekly MDR digest โ†’ allPLANNED
WhatsApp alert โ†’ TwilioOFF
Power BI feed โ†’ Supabase viewsCONFIG
๐ŸŽ“ Sandbox Mode โ€” Practice Environment
Enable Sandbox Mode to practice with mock documents without touching real UAQ data. Your live register is safely stored and returns instantly when you toggle Sandbox OFF.
Data separation: real docs โ†’ itqan_docs. Sandbox docs โ†’ itqan_docs_sandbox_backup. The two never mix.
Supabase Connection
Project URL
Anon Key
Settings โ†’ API in your Supabase project.
Never use the service_role key here. Anon key only.
UAQ Document Number Convention
Define what each segment of the UAQ official document number means. The system will decode any UAQ number automatically once you configure this.
1
2
3
4
5
6
7
Preview:
ITQAN Procedure Code โ€” How It Works
The ITQAN procedure code is generated automatically when you decode a UAQ number. It is never used in official correspondence. It drives all internal logic โ€” checklists, warnings, SLA rules, n8n automation, and signature requirements.

Format: ITQAN-T[Track]-[Discipline]-[DocType]-Rev[X]-[Mode]
ITQAN-T1-CV-DWG-RevA-NEW
Track 1 ยท Civil ยท Drawing ยท First submission ยท Standard procedure applies
ITQAN-T1-CV-DWG-RevB-RESUB
Track 1 ยท Civil ยท Drawing ยท Second cycle ยท Resubmission gate, one prior rejection
ITQAN-T1-ME-MTH-RevA-LEGACY
Track 1 ยท Mechanical ยท Method Statement ยท Backfilled โ€” pre-dates your tenure
ITQAN-T1-AR-DWG-RevC-GHOST
Track 1 ยท Architecture ยท Drawing ยท Placeholder only โ€” not yet in hand
The procedure code updates automatically โ€” you never type it manually. When Tracks 2โ€“5 are added, the code will reflect T2 (Correspondence), T3 (RFI), T4 (Contracts), T5 (Close-out) accordingly.
SLA Standards โ€” UAQ's Actual Review Periods
Enter UAQ's real contractual SLA period (in days) for each document type. Once set, new documents of that type default to the correct period automatically instead of a generic guess. Leave blank to keep the current default shown as a placeholder.
Reviewer Roster โ€” Who Reviews What
Assign the correct reviewer(s) to each discipline. Once set, the DC Process Checklist's "Route" step checks the assigned reviewer against this roster and blocks the step with a clear warning if it doesn't match โ€” instead of accepting any name typed into the document. Email is required to enable one-tap chaser emails; line manager email is optional and used for the 80% escalation cc.
SLA Early-Warning Threshold
The per-track DC ALERT banner flags a pending document as "approaching breach" once this % of its SLA has elapsed. Lower = earlier warning (more lead time, more noise). Default 80%.
% of SLA elapsed
Handover Checklist โ€” Close-out Completeness
The T5 Archive gate checks that every item on this handover checklist is present before a record is permanently archived. Edit this list to match what your handover dossier must contain.
โš ๏ธ These are generic industry-reference items, not your project's contractual requirements. Verify and adjust this list against the actual MASAR / UAQ contract O&M and close-out requirements before relying on it.
n8n + Power BI
n8n base URL
PBI endpoint
Power BI connects to Supabase via PostgreSQL connector. It reads the pre-built views directly โ€” no push needed. Supabase โ†’ Settings โ†’ Database โ†’ Connection string โ†’ URI mode.
Contractor Registry โ€” MASAR Destination
Tap a contractor to see their full document journey
โšก DC DAILY PRIORITY BRIEFING
Actions ordered by urgency and consequence ยท Proactive DC guidance
By Phase
By Contractor
By Discipline
By Status
Expected โ€” Not Yet In
STATUS: All ๐Ÿ”ด Overdue ๐ŸŸก Pending ๐ŸŸข Approved ๐ŸŸข Appr. w/ Comments ๐ŸŸ  Rejected โšช Expected
Construction Document Journey Map โ€” MASAR Destination
Tap a row label to filter ยท Tap a phase number for the full doc list ยท Tap any pill for live DC status
VIEW: All tracks โ€” tap a row label on the left to filter
STATUS: All ๐Ÿ”ด Overdue ๐ŸŸก Pending ๐ŸŸข Approved ๐ŸŸข Appr. w/ Comments ๐ŸŸ  Rejected โšช Expected
โ–ธ Show colour key
TRACK
17 docs
Pre-Construction
M1โ€“2
213 docs
Mobilisation
M2โ€“3
319 docs
Substructure
M3โ€“8
420 docs
Superstructure
M8โ€“18
522 docs
Envelope & MEP
M14โ€“24
620 docs
Fit-out & Finishes
M20โ€“28
712 docs
Completion
M26โ€“30
WHAT HAPPENSContracts signed. Programme set. Design finalised. Team mobilising.Site setup. Temp works. Piling plant arrives. First submittals issued.Piling. Pile caps. Ground beams. Basement walls. Waterproofing.Columns. Slabs. Cores. Structural steel. Frame rising.Facade. Roof. MEP rough-in. Lifts. Main plant installation.Partitions. Ceilings. Flooring. Joinery. FF&E.Commissioning. Testing. Snagging. As-builts. Handover.
T1 โ€” Shop Drawings
DWG ยท 14โ€“21d ยท Blocks construction
tap to filter
๐Ÿ“ Temp works dwg๐Ÿ“ Piling layout๐Ÿ“ Site hoarding๐Ÿ“ Pile cap details๐Ÿ“ Ground beam layout๐Ÿ“ Waterproofing details๐Ÿ“ Column schedule๐Ÿ“ Slab reinforcement๐Ÿ“ Steelwork connections๐Ÿ“ Facade panels๐Ÿ“ MEP coordination๐Ÿ“ Lift shaft details๐Ÿ“ Fit-out drawings๐Ÿ“ Ceiling layout๐Ÿ“ Flooring details๐Ÿ“ Snagging drawings
T1 โ€” Material Approvals
MAT ยท 14โ€“21d ยท Blocks procurement
tap to filter
๐Ÿงฑ Concrete mix design๐Ÿงฑ Reinforcement steel๐Ÿงฑ Waterproofing system๐Ÿงฑ Piling material๐Ÿงฑ Structural steel๐Ÿงฑ Formwork system๐Ÿงฑ Facade cladding๐Ÿงฑ Glazing system๐Ÿงฑ MEP equipment๐Ÿงฑ Floor tiles๐Ÿงฑ Joinery materials๐Ÿงฑ Paint system
T1 โ€” Method Statements
MTH ยท 14d ยท HSE ยท Blocks work start
tap to filter
๐Ÿ“‹ Mobilisation MS๐Ÿ“‹ Excavation MS๐Ÿ“‹ Piling MS โš ๏ธ๐Ÿ“‹ Dewatering MS๐Ÿ“‹ Waterproofing MS๐Ÿ“‹ Concrete pour MS๐Ÿ“‹ Formwork MS๐Ÿ“‹ Crane ops MS๐Ÿ“‹ Facade installation MS๐Ÿ“‹ Lift installation MS๐Ÿ“‹ Fit-out MS๐Ÿ“‹ Hazardous materials MS
T1 โ€” ITPs
ITP ยท 14d ยท Blocks all inspections
tap to filter
โœ… Site setup ITPโœ… Piling ITP โš ๏ธโœ… Concrete ITPโœ… Waterproofing ITPโœ… Structural ITPโœ… Welding ITPโœ… Facade ITPโœ… MEP ITPโœ… Finishes ITPโœ… Commissioning ITP
T1 โ€” Samples & Mock-ups
SMP ยท 14โ€“21d ยท Blocks finish work
tap to filter
๐ŸŽจ Concrete finish sample๐ŸŽจ Facade mock-up๐ŸŽจ Glazing sample๐ŸŽจ External finishes๐ŸŽจ Floor tile sample๐ŸŽจ Paint colour sample๐ŸŽจ Room mock-up
T1 โ€” O&M & Product Data
OAM ยท 21โ€“28d ยท Blocks handover
tap to filter
๐Ÿ“š MEP product data๐Ÿ“š Lift product data๐Ÿ“š Fit-out O&M๐Ÿ“š Fire systems O&M๐Ÿ“š Full O&M package โš ๏ธ๐Ÿ“š Warranties package
T2 โ€” Correspondence
Letters ยท NCRs ยท Notices ยท Minutes
tap to filter
โœ‰ Mobilisation noticeโœ‰ Programme submissionโœ‰ Site instructionsโœ‰ Meeting minutesโœ‰ NCRs โ€” pilingโœ‰ EOT noticeโœ‰ Progress minutesโœ‰ NCRs โ€” concreteโœ‰ EOT noticeโœ‰ Acceleration noticeโœ‰ NCRs โ€” MEPโœ‰ Technical minutesโœ‰ PC noticeโœ‰ Snagging NCRsโœ‰ Completion certificateโœ‰ Defects notice
T3 โ€” RFIs
7โ€“14d SLA ยท Urgent โ€” stops work
tap to filter
โ“ Design clarificationโ“ Site condition RFIโ“ Spec interpretationโ“ Piling RFIโ“ Ground condition RFIโ“ Structural RFIโ“ Coord clash RFIโ“ MEP routing RFIโ“ Facade interface RFIโ“ Fit-out RFIโ“ Commissioning RFI
T4 โ€” Contracts & Legal
No fixed SLA ยท Restricted access
tap to filter
โš– Main contractโš– Performance bondโš– Insurance certsโš– Sub-contractsโš– Early VOsโš– VO โ€” ground conditionsโš– Claim noticeโš– VO โ€” design changesโš– EOT assessmentโš– VO โ€” MEP changesโš– Prolongation claimโš– VO โ€” fit-out scopeโš– Final accountโš– Defects bond
T5 โ€” Close-out
As-builts ยท Handover ยท Blocks final payment
tap to filter
๐Ÿ— As-built starts โ€” substructure๐Ÿ— As-built โ€” structure๐Ÿ— As-built โ€” MEP๐Ÿ— Test records๐Ÿ— As-built โ€” fit-out๐Ÿ— Snagging register๐Ÿ— Handover dossier โš ๏ธ๐Ÿ— Completion certificate๐Ÿ— Commissioning records
โœ• Close
โœ• Close
Correspondence Register
โœ‰ Correspondence Guide โ–ผ
0
Pending
0
Overdue
0
Approved
0
Rejected
0
Expected
0
Total
Status
All
Pending
Overdue
Approved
Rejected
Expected
Document Type
All Types
โœ‰๏ธ Letters/Notices ยท LTR
๐Ÿ“ Minutes
โš ๏ธ NCRs ยท NCR
๐Ÿ“‘ Contract/Programme ยท CTR
๐Ÿ“Š Progress Reports ยท PRO
๐Ÿฆบ HSE Records ยท HSE
Correspondence Register
LEGEND: โœ‰๏ธ LTR โ€” Letter / Notice ๐Ÿ“ MIN โ€” Meeting Minutes โš ๏ธ NCR โ€” Non-Conformance Report ๐Ÿ“‘ CTR โ€” Contract Doc ๐Ÿ“Š PRO โ€” Progress Report ๐Ÿฆบ HSE โ€” HSE Record
RFI Register
โ“ RFI Guide โ–ผ
0
Pending
0
Overdue
0
Approved
0
Rejected
0
Expected
0
Total
Status
All
Pending
Overdue
Approved
Rejected
Expected
Discipline
All Disciplines
Civil
Arch
Mech
RFI Register
Contract Register
๐Ÿ’ฐ Contracts Guide โ–ผ
0
Pending
0
Overdue
0
Approved
0
Rejected
0
Expected
0
Total
Status
All
Pending
Overdue
Approved
Rejected
Expected
Document Type
All Types
๐Ÿ’ฐ Variation Orders ยท VO
๐Ÿ“‘ Contract Docs ยท CTR
๐Ÿ“œ Contract Agreement ยท CNT
โ›” Termination ยท TER
Contracts Register
LEGEND: ๐Ÿ“‘ CTR โ€” Contract Doc ๐Ÿ’ฐ VO โ€” Variation Order ๐Ÿ“œ CNT โ€” Contract Agreement โ›” TER โ€” Termination
Close-out Register
๐Ÿ Close-out Guide โ–ผ
0
Pending
0
Overdue
0
Approved
0
Rejected
0
Expected
0
Total
Status
All
Pending
Overdue
Approved
Rejected
Expected
Document Type
All Types
๐Ÿ“ As-Builts
๐Ÿงช Test/Snagging
๐Ÿ Handover
Close-out Register
Documents
โœ•
Claude โ€” DC Intelligence
Analysing project context...
โœ•
Analysing...
Responses are generated by Claude AI. Always verify against your project contract and UAQ procedures before acting.